Committee hears updates on natatorium roofing, boilers, JTL studio and other projects
Summary
Facilities staff reported progress across multiple capital projects: the high school natatorium roof is roughly three-quarters complete with a projected early-October finish, several boiler replacements are on schedule, the JTL studio renovation awaits stamped drawings and permits, and staff recommended budgeting for worn lockers.
Facilities staff presented progress reports on a slate of capital projects during the Property Facilities Committee meeting.
Josh, a facilities staff member, reported that the high school natatorium roofing is about 75% complete. He said Mun Roofing has been on site, crews addressed several conditions behind a wall, and staff expects the roof to be weathertight. Josh projected a finish date “by, say, October 10,” describing that as about a week to 10 days from the meeting date.
On the North…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat