Summary
City staff and Imperial Irrigation District (IID) representatives briefed the council on a change order to a contractor (GCX) for IID off‑site power work serving a new development; staff said the change order is within the existing budget but will delay energization to January 2026.
City staff and Imperial Irrigation District (IID) representatives told the Indio City Council on Oct. 1 that a change order to the GCX contract for IID off-site power work is necessary to complete electrical service for several pending developments and will delay full energization until January 2026.
Jose Ramirez, principal management analyst for the city, said the work is part of the city's obligation under a cooperation agreement with Candu LLC, the Greens developer. The scope covers off-site IID work to bring power to the northeast corner of Avenue 40 and Jackson Street and will enable energization of…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat