Central Valley construction reaches 61% guideway completion; railhead in yard readying for material deliveries
Summary
Chief of Construction Edward Fenn reported July 2025 construction progress for the Central Valley: guideway about 61% complete, 72 miles of guideway finished, 55 structures complete (correction), utility relocations largely complete and railhead work substantially finished for staging.
Edward Fenn, the authority’s chief of construction, briefed the Finance and Audit Committee on Oct. 9 on Central Valley construction progress through July 2025, reporting steady monthly expenditures, structure completions and utility relocations that support the upcoming track-laying phase.
Fenn reported $87.4 million in construction expenditures for the month, with the majority spent on Construction Package 1 (CP 1). He told the committee the guideway is roughly 61% complete on a 119-mile initial operating segment, with 72 miles complete, 28 miles underway and 19 miles not started. "For guideway, we had completed we're basically 61% complete with guideway for 72 miles total,"…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat