District approves final payouts to Brackney for Wharton area improvements
Summary
The board approved two payouts to Brackney totaling roughly $243,060 to close out the Wharton area improvements contract, with the project entering warranty period.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Delaware County Regional Wastewater District authorized final payments to contractor Brackney to close out the Wharton area improvements project.
Staff reported two payouts: $37,059.17 to complete punch‑list work and $206,001.29 as the final retainage payment. "That's getting everything buttoned up on the punch list... that's their last retainage. So this pretty much closes out on their side for Brackney," staff said. The board approved the payments on a voice vote.
Staff indicated the project will likely enter the warranty period and that any outstanding invoices from the current month would be presented separately. The board asked staff to prepare a summary of remaining bond balances and any items that might be returned to the bond fund for the next meeting.