Clay County permits winter hauling at Westland Excavating gravel site with modified hours
Summary
The Planning Commission approved an interim use permit amendment for Westland Excavating to allow hauling, stockpiling and maintenance activities during the first quarter (January–April) using paved routes; excavation/expansion remains limited to April–Dec. 1 condition (number 9) was amended; county engineer raised no objection.
Get email alerts on the Mining Aggregate topic
No spam. Unsubscribe anytime.
The Clay County Planning Commission on Aug. 20 approved an amendment to an existing interim use permit for Westland Excavating that allows certain hauling, maintenance and stockpiling operations during the first quarter of the year while preserving seasonal limits on excavation.
The operator sought a modification that would permit hauling, stockpile removal and related non‑excavation activity year‑round (including January through April), while excavation and pit expansion would remain limited to the established April 1–Dec. 31 window and standard hours. The county engineer reported no objection; staff said the change is feasible because the site’s primary haul routes are paved.
Planning staff explained Condition 9 on the current permit limits mining operations to April 1–Dec. 31, 7 a.m. to 7 p.m., Monday–Saturday, with no noise‑producing operations on Saturday. The proposed amendment allows hauling and maintenance outside that April–Dec. excavation window but keeps excavation and expansion within the current seasonal window. It also requires that hauling during posted seasonal load restrictions use paved roads or other routes approved in writing by the highway department or township road authority.
Jeff (Westland Excavating) told commissioners he expects winter work to be primarily movement from stockpiles and delivery of sand for winter projects and does not anticipate active excavation in Minnesota winter conditions. Planning staff also noted that gravel tax reporting is self‑reported quarterly and that first‑quarter reports often show no removals; some operators have reported first‑quarter movement, which helps explain the applicant’s request.
Commissioner Ashley moved to approve the permit amendment, the motion was seconded and carried on voice vote. Staff said the 12 existing permit conditions remain in force, with the modification to condition 9 as requested. The county will require the operator to notify the Planning Office when extended hours are needed, and property owners may be notified when extended operations are approved.
The commission concluded the amended interim use will not injure public health or surrounding property and that appropriate measures for utilities, access, drainage and nuisance control remain in place. The operator must continue to comply with county conditions and obtain any required approvals from township or highway authorities for routes used during seasonal load restrictions.