MidAmerican says last Page County turbines should be topped off by Halloween; transformer delivery scheduled
Get AI-powered insights, summaries, and transcripts
Sign Up FreeSummary
MidAmerican reported a final transformer delivery and said seven turbines remain in Page County, with the last expected to be topped off by Halloween; company representatives said two crane crossings remain and promised verification of turbine models and permit compliance.
A MidAmerican representative told Page County supervisors the project's final large delivery, a transformer for the substation, is scheduled to arrive this week and that seven wind turbines remain to be topped off in Page County. The representative said the last turbine is likely to be topped off by Halloween.
The company noted there will be traffic impacts from crane crossings and said only two crane crossings remain in Page County, with one tentatively planned for Thursday the 23rd at C Avenue between turbines 14 and 15. A county supervisor asked whether turbines near residences had been built to smaller specifications agreed in a settlement; the company said building-permit records reflect those terms and offered to email verification of turbine models and permit compliance.
Ending: MidAmerican representatives promised to provide documentation to the county confirming turbine models and building permits and to continue coordinating crane crossings with county engineers as construction winds down.