City Council approves $126,000 contract for NE Tenth Avenue construction-phase engineering
Summary
Canby City Council moved on April 2 to authorize the city administrator to sign a $126,000 contract with Curran McLeod Incorporated for construction-phase engineering on NE Tenth Avenue (N. Locust to N. Pine). Council set a second reading for April 16, 2025; councilors said the city remains under budget on the project.
Get email alerts on the Street Reconstruction topic
No spam. Unsubscribe anytime.
The Canby City Council voted to move Ordinance 16‑41 forward to a second reading on April 16 after approving a contract authorization for construction-phase engineering on NE Tenth Avenue.
Public works staff told the council the Tenth Avenue project — which includes sewer, pavement and other work — is a large reconstruction effort. The city solicited proposals for construction-phase engineering and selected Curran McLeod Incorporated for $126,000. Staff said Curran McLeod was the only proposer and that the firm had performed prior design work on the project. Construction is scheduled to begin April 14, with a requested one-week extension around the fair, and the project is expected to be completed in October.
Councilor Patton moved to approve Ordinance 16‑41 authorizing the city administrator to execute the contract; Councilor Davis seconded. The motion carried by voice vote; the ordinance advances to a second reading on April 16, 2025.
Staff said the project remains under budget despite the additional contract for construction-phase engineering.
Next steps: staff will finalize the contract with Curran McLeod, provide construction-phase engineering support during the active construction period and return for the formal second reading of the ordinance on April 16.