Town hall renovation moves ahead; asbestos abatement and flooring work complete, move planned for November
Summary
Officials reported progress on the new town‑hall project: asbestos abatement in multiple rooms is done, flooring work has started, door controls and signage are being arranged, and Pioneer Movers is scheduled for a mid‑November move; staff warned of brief service disruptions during the move.
Town administrators updated the Select Board on the town‑hall renovation and planned move during the Oct. 20 meeting, reporting that asbestos abatement in five rooms is complete and that flooring and related finish work are underway.
Staff said the contractor completed abatement for five rooms last week and expected the remaining two library‑adjacent rooms to be finished the same week.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat