Summary

Public Works staff described a proposed five‑year lease with a $1 buyout for a rubber‑tire front‑end loader, reported nearly $13,000 in recent repairs to the current loader, and said the 23‑year mini excavator is out of service and will be surplused via GovDeals or traded.

Public Works staff told the committee the city plans to lease a new rubber‑tire front‑end loader on a five‑year lease with a $1 buyout so the city will own the machine at the end of the lease.

The director said the city spent just under $13,000 on repairs to the current loader over the past 18 months (new tires, wiring harness, circuit board and miscellaneous repairs) and that the loader is used about 300 hours per year for attachments such as a reach‑arm mower. The director said the reach‑arm attachment saved the city roughly $100,000 compared with buying a separate tractor and attachment several years ago.

Staff said the current mini excavator is 23 years old, is out of service, needs new tracks and other major repairs and is not safe or reliable to send into service. The director said staff plans to list surplus units on GovDeals or negotiate a dealer buyback; any trade‑in or sale would be a separate transaction from the lease purchase.

Storage and operations: committee members raised where new equipment would be stored if the city consolidates facilities. The director said Holman and other satellite buildings have been used to cycle equipment and that, depending on the final facility plan, the city may need to retain some existing units for space and operational continuity.