Commissioners approve $1.26 million change order for Smilax Road lift station project after unforeseen railroad permit work
Summary
The board approved Change Order No. 1 to CNE Excavating for the Smilax Road lift station and force main project, increasing the contract by $1,262,943.70 to cover a required grouting program and other unforeseen items tied to railroad permit conditions; staff said portions of the cost are expected to be paid by Amazon.
The St. Joseph County Board of Commissioners approved Change Order No. 1 to the CNE Excavating contract for the Smilax Road lift station and force-main project at its Oct. 21 meeting. The change order increases the contract by $1,262,943.70.
Infrastructure staff explained that Norfolk Southern…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat