Council awards $7.95 million Paraty Park harbor reconstruction contract; project tied to November bond vote
Summary
The council voted 4-1 to award a nearly $8 million contract for the Paraty Park shuttle landing, seawall and floating dock reconstruction. Councilors debated timing, cash flow and the project's relationship to an infrastructure bond the city plans to sell in January.
Get email alerts on the Paraty Park topic
No spam. Unsubscribe anytime.
The Newport City Council voted 4-1 to award a contract to Reagan Marine Construction of Newport for the Paraty Park harbor shuttle landing, seawall and floating-dock reconstruction, with a contract cost not to exceed $7,949,000.
The council and staff described the project as a time-sensitive, multi-part waterfront reconstruction tied to the municipal infrastructure bond voters approved in November 2024. City staff said the vendor selection followed evaluation of three proposals and that Reagan Marine offered the best value and schedule for the work.
Council questions focused on funding timing and cash flow. Several councilors asked how the city will pay invoices that may arrive before bond proceeds are received in the market. The director of finance said the bond sale is planned for January and that the city manages pooled cash flows to meet near-term obligations while bond proceeds are finalized. The project team explained that long-lead items such as prefabricated docks can take more than a year to manufacture and ship, which is why the procurement is being advanced now.
Why this matters: The Paraty Park work includes a new shuttle landing and a reconstructed seawall and floating dock that the city and project supporters say are necessary to support harbor operations and visitor access. Project proponents said moving now reduces schedule risk and secures production slots for docks and pilings.
Opponents and skeptics asked for clarity on cash flow and the effect on other capital priorities; one councilor said the project had not been budgeted as an immediate cash outlay and pressed administration staff for detail on how expenses will be handled before bond proceeds arrive.
Vote and next steps: The council approved the construction contract 4-1. Staff said construction will be staged to match cruise-ship seasons and permitting timelines; design tasks and further procurement steps remain, including hiring an architect for the site building and public-input work on the park design. Staff said invoices will be billed as project milestones are met and that the city expects a lag between procurement and major cash outlays because of fabrication and shipping timelines for dock components.