Committee backs $0-net change order for North Penn High bid package 1; $212,961 in work covered by allowances
Summary
The committee recommended approval of a general-contractor proposed change order totaling $212,960.64 that will be paid from existing allowances rather than increasing the contract or project budget.
Get email alerts on the Construction Management topic
No spam. Unsubscribe anytime.
The Facilities and Operations Committee recommended approval of a general-contractor change order for bid package 1 at North Penn High School totaling $212,960.64. District staff said the change is a $0-net change order — meaning the contract sum and project budget will not increase because the work will be paid from existing allowances.
Staff listed scope items covered under the change order, including tree removal, remediation of unexpected rock, additional bollards and gates, wet-bed tile installation in the pool area, an additional pipe chase, deductions for changed utility scopes and additional liquid/tank removal resulting from infiltration. “A lot of the dollars that are involved in this change order are based upon conditions in the exterior of the building,” a district representative told the committee, adding that exterior work in bid package 1 is substantially complete and that project risk related to the exterior has diminished.
Committee members thanked staff for detailed review, and staff said remaining allowances and contingency are sufficient to absorb the work without increasing the contract amount. The committee voted to recommend the change order; no opposition was recorded.
Staff said they do not anticipate a large number of additional change orders for bid package 1 beyond typical unforeseen conditions encountered during construction.