Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction Management topic

No spam. Unsubscribe anytime.

Committee backs $0-net change order for North Penn High bid package 1; $212,961 in work covered by allowances

5870952 · September 30, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee recommended approval of a general-contractor proposed change order totaling $212,960.64 that will be paid from existing allowances rather than increasing the contract or project budget.

The Facilities and Operations Committee recommended approval of a general-contractor change order for bid package 1 at North Penn High School totaling $212,960.64. District staff said the change is a $0-net change order — meaning the contract sum and project budget will not increase because the work will be paid from existing allowances.

Staff listed scope items covered under the change order, including tree removal, remediation of unexpected rock, additional bollards and gates, wet-bed tile installation in the pool area, an additional pipe chase, deductions for changed utility scopes and additional liquid/tank removal resulting from infiltration. “A lot of the dollars that are involved in this change order are based upon conditions in the exterior of the building,” a district representative told the committee, adding that exterior work in bid package 1 is substantially complete and that project risk related to the exterior has diminished.

Committee members thanked staff for detailed review, and staff said remaining allowances and contingency are sufficient to absorb the work without increasing the contract amount. The committee voted to recommend the change order; no opposition was recorded.

Staff said they do not anticipate a large number of additional change orders for bid package 1 beyond typical unforeseen conditions encountered during construction.