County reports microsurfacing, paving and shop/bridge work; some traffic changes expected at Osmus intersection

5856800 · September 30, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Secondary Roads staff reported microsurfacing plans on Winnebago Church Road, final paving steps on several routes, shop relocation progress, and an upcoming bridge box‑installation on Buffalo project; shoulders, striping and signs remain to finish paving work.

Secondary Roads staff briefed Winnebago County supervisors on pavement and capital projects and outlined remaining work.

Scott (Secondary Roads staff) said microsurfacing might happen this week for Winnebago Church Road pending availability of aggregate and mix design. Paving work on a separate project is complete, and crews will add shoulders, paint pavement markings and install rumble strip panels and permanent signs; staff said the contractor will return for rail transition repairs but the county will not delay striping for those patches.

Staff reported trucks placed rock driveways for a hospice access and that shoulder work from Osmus back to town was imminent. At one intersection, the board was told the traffic control pattern will change: stop signs will be posted on the north and south approaches while east‑west traffic will be through movements, and “pavement ends” signs will be added.

On the shop project, crews have moved into the new facility, finished much of the interior, and were pouring a concrete pad for scrap and fuel barrels; asphalt work for the salt shed pad remained. The county also reported a bridge removal and replacement project (Buffalo 25/4) with box culvert delivery and crane coordination expected in the coming weeks.

Supervisors approved interim contract closeout steps for surfacing projects and were told final payments will follow federal closeout procedures for federally funded work.