Votes at a glance: Arvada council approves infrastructure change order and appoints relief judge

5717629 · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On Sept. 2 the Arvada City Council approved a contract change order for the 2024 Water Main Replacement Project and appointed Alexa Visscher as a municipal court relief judge; both items passed unanimously.

A quick summary of other formal actions taken by the Arvada City Council on Sept. 2:

R25-073 — Water main change order (approved 5–0): Council approved Change Order No. 2 to the contract with EZ Excavating Inc. for the 2024 Water Main Replacement Project (project 24-WA-01). The change order increases the contract by $681,646.35, bringing the total contract amount to $5,511,655.35. Staff said the work replaces asbestos-cement water lines in the Sierra Vista neighborhood and addresses capacity and replacement needs at Kipling and West 80th Avenue and Alkire Street; staff described the replacement as necessary because the AC pipe has reached the end of its useful life.

R25-074 — Employment agreement appointing a municipal court relief judge (approved 5–0): Council approved an employment agreement appointing Alexa Visscher (also referred to as Alexa Fisher during the swearing-in) as a municipal court relief judge under Arvada City Code ACC 58-74. The appointment will be memorialized in an annual employment agreement as provided by city code; the council conducted a brief swearing-in following the vote.

Votes and absences: Both items passed unanimous votes among the five members present. Council Members Pfeiffer and Ambrose were excused from the meeting.

Context: The water main project work replaces aging asbestos-cement pipe and aims to reduce long-term maintenance disruptions and capacity risks; the court appointment follows the code process for relief judges and was supported by city attorney staff.