Waverly Utilities starts 50-year transmission rebuild; supply chain delays keep one wind turbine offline
Summary
Staff began a long-planned transmission rebuild and reported supply-chain delays on wind turbine blade motors with 16–20 week lead times; broadband work continued and the utility reported a Windstream outage and a video-content price increase from ESPN/Disney.
Waverly Utilities staff reported operational updates to the Board of Trustees, including the start of a major transmission-line rebuild, a wind-turbine outage tied to long lead times for replacement motors, and ongoing broadband work.
Kurt (staff member) said crews began rebuilding a 50-year-old transmission line between the Westload and Southload centers; the project will replace poles, overhead infrastructure and wires, and staff expect to complete primary contractor work by November. "That transmission line is 50 years old. Life expectancy…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat