City reports progress, delays and time-only extension on MAPS bike lanes
Summary
Consort Engineers updated the MAPS 4 Citizens Advisory Board on construction progress for bike lanes phases 1A and 1B, reporting pavement repairs, signal upgrades, installed striping and a no‑cost 48‑day schedule extension due to weather and additional work.
Consort Engineers provided a construction update on MAPS for Bike Lanes phases 1A and 1B at the Sept. 4 MAPS 4 Citizens Advisory Board meeting, reporting pavement repairs, striping totals, signal upgrades and a time‑only schedule extension for weather and additional work.
Project engineer Josh Malwick described phase 1A limits—including Northwest 16th Street (Overholser Trail to Tulsa Avenue), Tulsa between 16th and 19th, and 19th Street between Tulsa and Indiana—and said crews installed protected and shared facilities where space allowed. “Tier 1 protected bike lanes… have the individual bike lanes separated by traffic,”…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat