Council awards $14.7 million contract for Ninth Street corridor upgrades, including three roundabouts

5825569 · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City awarded construction and construction-management contracts for the Ninth Street Corridor Improvement Project, funded by AHSC, Measure L and local funds; work includes three single-lane roundabouts and multi-modal improvements.

The Modesto City Council voted unanimously Sept. 23 to award contracts to construct the Ninth Street Corridor Improvement Project, a multi-phase street, bicycle and pedestrian upgrade stretching from Carpenter Road to L Street.

City Engineer Toby Wells told the council the project had been advanced with an Affordable Housing and Sustainable Communities (AHSC) grant and local Measure L funds. The winning low bidder for construction was United Pavement Maintenance, at $13,363,465; the council authorized change orders up to $1,336,347 (10%) for a total not to exceed $14,699,812. The council also approved a construction-management agreement with TRC Engineers not to exceed $990,880, plus a 10% additional-services authorization (total not to exceed $1,089,968).

Wells described three single-lane roundabouts planned at Carver, Tully and Needham to address offset intersections and improve safety, plus roadway, bus-stop and bicycle-path improvements. The project will be built in two phases; the north segment (Needham to Carpenter) will be constructed first with the south segment following in 2026.

Council members asked technical questions about right-of-way and utilities; staff said the work stays within existing city right-of-way and that sidewalks, landscaping and non-electric utilities would be preserved. The council authorized the manager to execute the contracts and approved a budget amendment to allocate additional funds to complete the project. Wells estimated construction would start late 2025 with substantial completion targeted across 2026–27.

The contract award and construction-management agreement carried on a 7–0 roll call vote.