Winnebago County approves new courthouse annex boiler; discusses generator upgrade and approves several permits and claims

5823844 · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisors voted to replace a deteriorating boiler in the courthouse annex and approved a utility permit and a tile crossing payment. The board also approved county claims and payroll; discussion about a generator upgrade for public health was tabled pending more bids and budget review.

Winnebago County supervisors voted to replace the aging boiler in the courthouse annex and approved a set of routine permits and payments during their meeting.

The board approved moving forward with a new boiler for the courthouse annex after staff presented quotes and lifecycle concerns for the existing unit. Kevin, a county staff member, told supervisors the current boiler is near the end of its service life and warned that replacement parts can take weeks to arrive. “I think we should strongly consider just replacing it and being done with it rather than take the chance of, you know, in the middle of winter, I just I come in 1 morning and it's 60 degrees in here,” Kevin said.

The board voted on related maintenance and funding matters. Supervisors also approved a utility permit for WCTA to bury fiber to service a new house north of Buffalo Center, and approved payment of a county share for a private tile crossing permit for a landowner in Mount Valley Township where the contractor’s estimate exceeded the county’s administrative limit. The board approved county claims and payroll as presented.

Nut graf: The boiler replacement decision responds to repeated service warnings and an internal estimate placed in the county’s fixed-plant equipment repairs budget. Supervisors approved the single-boiler replacement for the newer portion of the courthouse while continuing discussion and fact-finding on a separate backup generator for the public health building.

Board discussion and votes Kevin described prior quotes and told supervisors a replacement unit estimate listed one line item at "33,640," with roughly $4,000 identified as labor and about $27,000 as materials. He said the single new boiler would not provide redundancy but would reduce the risk of an extended outage during winter.

Supervisor Derby moved to proceed with the boiler replacement for the new portion of the courthouse; Supervisor Genswold seconded the motion. The board took a voice vote; the motion passed.

On the tile crossing permit for Brian Miller (Mount Valley Township, sections 26–27), staff reported the contractor completed a 12-inch crossing and the estimate exceeded the county’s $2,500 administrative payment limit. Supervisors discussed precedent and workload constraints that led a landowner to hire a contractor immediately instead of waiting for county crews. Supervisor Smith moved to pay the county’s share above the $2,500 administrative limit; Supervisor Derby seconded. The motion passed.

Supervisors also approved a utility permit allowing WCTA to bury fiber to serve a new private residence north of Buffalo Center. Jen Swope made the motion to approve the permit; another supervisor seconded and the motion passed.

The board approved county claims and payroll by voice votes during the meeting.

Generator for public health: discussion tabled Staff presented an estimate to replace an undersized public-health generator (the current unit dated to 2011 and only supplied limited outlets during outages). Staff reported the proposed replacement would be a 110-amp (air-cooled) unit with an updated transfer switch to power additional outlets in the immunization/treatment room. The county’s public-health staff said some grants could be pursued but required multiple bids and matching funds; supervisors asked for additional bids and clearer specifications and tabled any immediate action on the generator until they had more information on sizing, cost, and budget availability.

Votes at a glance - Approve minutes and agenda: Motion by Derby, second by Genswold; outcome: approved. - Approve WCTA utility permit to bury fiber optic to serve a private residence north of Buffalo Center: mover Jen Swope, second Derby; outcome: approved. - Approve county payment share for tile crossing permit (Brian Miller, Mount Valley Township) where estimate exceeded the $2,500 administrative limit: mover Smith, second Derby; outcome: approved. - Approve replacement of the courthouse annex boiler (single new unit for the newer section): mover Derby, second Genswold; outcome: approved. - Approve county claims: mover Derby, second Genswold; outcome: approved. - Approve payroll: mover (record shows motion and second); outcome: approved.

Ending: Supervisors instructed staff to gather additional bids and specifications for the public-health generator and to verify grant and budget options before returning the item for a future decision. County staff will proceed with contracting activity for the approved boiler replacement and process the approved permits and claims.