Newport News officials report Huntington Middle School on track for June 2026 substantial completion
Summary
City and school officials updated the joint work session on construction progress at the Huntington Middle School and adjacent recreation center, citing current percent-complete, costs, encountered buried tanks and remaining critical-path items including a transformer and stormwater work.
City and school officials on Sept. 23 updated the Newport News City Council and School Board on construction at Huntington Middle School and the adjacent recreation center, saying the middle school is on track for substantial completion in June 2026 and the recreation center in August 2026.
Craig Gallant, director of engineering for the City of Newport News, told the joint work session that contractors began work after a notice to proceed in June and are currently about 36–37% complete on both facilities. "The middle school itself is 123,000 square feet, approximately. The rec center is just a little bit over 97,000 square feet," Gallant said. He added that the project was awarded as a single contract but that the contractor is using two teams — one for each facility — which is why percent-complete figures for both buildings look similar even though the school has priority.
The project budget figures presented at the meeting list the school…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat