Bee Cave Parkway sidewalk project reaches 30% design; board warned of a potential $5,000 overrun
Summary
BCDC staff said the Bee Cave Parkway sidewalk and pedestrian-crossing improvement project is in 30% design and will require a TxDOT submittal; the design team estimates the project may be about $5,000 over a $400,000 budget and could prompt a future budget amendment.
BCDC staff reported Sept. 23 that the Bee Cave Parkway sidewalk and pedestrian-crossing improvement project has reached the 30% design stage and requires a submittal to the Texas Department of Transportation for the crossing on State Highway 2244.
A staff presenter said the design team is finalizing a 30% submittal required by TxDOT and that work is proceeding toward a 60% preliminary…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat