Residents press commission on subdivision quality, drainage and signage; staff says enforcement stepped up
Summary
Residents raised concerns about landscaping, drainage and construction quality in several subdivisions; planning staff said enforcement and interdepartmental inspections have increased and that letters and permits are being used to address violations.
Get email alerts on the Code Enforcement topic
No spam. Unsubscribe anytime.
Several residents used the planning commission's miscellaneous business and public-comment time to press the city on construction quality, drainage and landscaping in Crown Point subdivisions, and planning staff described stepped-up enforcement and coordination with other departments.
At the meeting a longtime resident raised concerns about Summer Tree and Providence subdivisions, saying contractor work was low quality and that ditches were not draining. The resident said he had a negative confrontation with a project supervisor and was worried about developers seeking bond release before correcting drainage problems.
Planning staff (identified in the transcript as Josh and other staff) said the department has updated landscaping requirements and is addressing outstanding issues during the review process. Staff reported an increase in enforcement work: the transcript records roughly 90 violation letters several years ago, about 128 violation actions this year, and a recent sharp decline in temporary "for sale"/"buy homes" signs as inspectors and other departments remove signage. Staff said they first try phone calls and letters to open a dialogue and set remediation timetables; persistent noncompliance is referred to the city's legal department and civil court.
Resident Susan McKendree said the meeting was "the most refreshing meeting I have been in in the city in a year," praising the commission's proactive approach. Another resident, Sam Casitis, complimented the Greenwood/Smith Farm presentation and welcomed the phased approach compared with larger, denser proposals he said he had seen elsewhere.
Staff said inspectors from other departments are assisting by documenting violations in the field and removing temporary signage; a recent count cited during the meeting showed about 18 temporary signs remaining at one point before removals. Staff also said a letter had already been sent in at least one noted case and that drainage concerns are a known sticking point for bond release on some subdivisions.
No formal action or vote resulted from the miscellaneous business portion of the meeting; staff said they will continue enforcement, continue to work with public works and engineering on drainage issues, and that legal referral is used when property owners refuse to comply.