Supervisors ask for final closeout numbers on $133M jail relocation; public works says project remains under budget

6441434 · September 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisor Ramos asked Public Works for a final, itemized closeout total for the county's new detention facility and associated change orders. Public Works Director Steve Leder told the board the project is under budget and that a state closeout audit will start next month; the board approved the associated consent item unanimously.

NAPA, Calif. — Napa County supervisors asked staff Sept. 23 to return with a final, fully reconciled total for the county’s new detention facility after accounting for furniture, change orders and other closeout costs; Public Works told the board the project remains within available funding and a state closeout audit will start soon.

Lede: During consideration of consent and closeout items, Supervisor David Ramos requested a comprehensive “final final” cost tally for the detention facility relocation project that includes all change orders, furniture and last-minute operational upgrades. Public Works Director Steve Leder reported the project remains under budget and said the county will complete state-required closeout steps and an audit in coming months.

What was said Supervisor Ramos asked staff for an accounting of the project’s final cost: “What I would like to be able to have, come back to us is, the final final cost. Throw in the furniture, throw in these change orders, and tell us what that final cost was.”

Public Works Director Steve Leder: “We are not close to needing more money from you. Trust me on that. We did have a number of items in closeout…there is a closeout audit with the state that happens as part of this project, and that's I believe scheduled for next month.”

Leder explained several final items that contributed to change orders, including last‑minute code and safety changes requested by the Board of State and Community Corrections (BSCC) related to fixtures and bunk beds, additional EV chargers added to meet the county’s climate policy, and final work on security and telecommunications identified during operational testing.

Board action The board approved the related consent item (item 5U) on a unanimous vote; Supervisor Ramos made the motion and Supervisor Manfry seconded. The board directed Public Works to return with the reconciled final cost after the state closeout audit is complete.

Provenance (transcript evidence) Supervisor Ramos raised the question during the consent follow-up discussion; Steve Leder responded with the status update that the project was under budget and that a state closeout audit is imminent.

Practical note Public Works said they expect the definitive reconciled number to be available after the state audit and closeout processes, which staff estimated would take a couple of months.