Committee approves rehabilitation plan for Fairmount Bridge in Hunting Valley

6438549 · September 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cuyahoga County Public Works committee approved a resolution declaring the need to rehabilitate Fairmount Bridge No. 10.8 over the Chagrin River in Hunting Valley, with an estimated construction cost of $2.3 million and construction scheduled for 2027–2028.

The Cuyahoga County Public Works Procurement and Contracting Committee on July 30 approved Resolution 20250266, declaring that public convenience and welfare require rehabilitation of Fairmount Bridge No. 10.8 over the Chagrin River in the village of Hunting Valley.

Eric Mack, Public Works, told the committee that the bridge deck is deteriorating and estimated the construction cost at $2,300,000. "The existing bridge deck is falling apart, so we need to repair it," Mack said, adding that the bridge was built in 1941 and last rehabilitated in 1976. He said construction is anticipated to begin in 2027 with completion in 2028 and that staff will seek additional grants to supplement the county estimate.

The committee asked about traffic. The presenter said the bridge carries about 3,600 vehicles per day. A committee member thanked staff for maintaining the county's bridges.

The committee moved and seconded the resolution and voted in favor. The committee chair indicated the measure will proceed under the standard three-reading process; no suspension of the second reading was requested.

Next steps will follow the county's legislative calendar for multi-reading measures and any grant-seeking by Public Works prior to construction.