Construction bond update: Waxahachie ISD reports 85% completion overall for Waxahachie Creek site; delays on track work tied to utility coordination
Summary
District staff reported progress across bond projects including Coleman, Findlay and Howard junior highs, the Waxahachie Creek High School site (~85% complete overall) and playground upgrades under Proposition C; some items delayed by utility coordination and weather.
District construction staff provided the board with a September 2025 update on work funded by the 2023 construction bond, reporting progress across several campuses and noting schedule constraints tied to outside utilities and weather.
Coleman Junior High: The district reported that interior warranty punch-list work is complete; outstanding exterior work on the track and field is delayed because Charter Communications must relocate fiber and a pole that currently sits in Lane 5 of the track. Contractors and district staff said funds have been provided and the district is awaiting scheduling from the utility before asphalt and concrete work can be…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat