CTE and Riverview construction progress: roofs, stairs and parking-lot work on schedule; sanitary tie-in may affect bussing
Summary
Staff reported roofs are on at CTE and Riverview, stairs for Riverview’s second floor should arrive this week, windows are scheduled, and mid-October parking lot surfacing at Riverview is expected. Staff cautioned a sanitary tie-in at the CTE building may disrupt bussing for a day or two.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Facilities staff provided a construction update noting that roofing is in place at both the CTE building and Riverview. Riverview is expected to receive stairs to the second floor this week; floors in the commons and bistro area at the CTE building were finished recently and electrical work is underway.
Staff said windows are scheduled and mid-October has been targeted for the Riverview parking-lot surface work. The team is discussing a sanitary tie-in at the CTE building; staff said that work "may disrupt our bussing for a day or two" and that planning continues to minimize impact.
Staff also said construction meetings are addressing timing and sequencing to reduce interruptions and that they will coordinate to avoid major bussing problems if possible.
Ending
Staff asked the committee to note these near-term milestones; no formal approvals were sought during the update.