Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Fire Station Renovations topic

No spam. Unsubscribe anytime.

Board approves three change orders extending Fire Station 3 work after permit delays

5821015 · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Public Works approved three change orders on Sept. 23 extending completion dates for Fire Station 3 renovations by two weeks and three days after permit delays for new electrical service.

The Bloomington Board of Public Works voted unanimously Sept. 23 to approve three identical change orders that extend contractor completion dates for renovations at Fire Station 3.

Adam Wiesen, speaking for Facilities Director J.D. Boroff, said the change orders extend the contracts by two weeks and three days to a new substantial completion date of Sept. 12, 2025. The extensions were necessary after staff experienced delays in obtaining permits for the new electrical service that was part of the renovation work.

The board approved change order No. 1 for Woods Electric Contracting, Building Associates and Commercial Services. Each motion to approve the respective change order passed on roll-call votes; Caron, Roach and Board President Kyla Cox Deckard voted yes on each.

Wiesen described the approvals as administrative extensions tied to permitting timelines rather than changes to project scope or budget in the meeting record. The board’s action keeps the Fire Station 3 renovation schedule aligned across the multiple prime contractors while staff finish permit processing.

Board members did not request further briefing on additional costs in the meeting record; the staff report presented the change orders as time adjustments tied to permit approval timing.

The board then moved to other agenda items.