Public works: $20,812 change order approved for Strong Street project; Martin Road crosswalk estimate presented
Summary
Public works described a $20,812 change order for Strong Street work after crews found additional damaged concrete; the department also proposed a $13,475 crosswalk pad at Martin Road with an optional $5,000 flashing light and agreed to test a half‑hour loading zone for Pace's Pizza.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Jamestown public works committee reported a change order and several street‑infrastructure items for council consideration.
Staff explained that while excavating on Strong Street (between Lakeview and Prendergast), contractors discovered additional degraded sections requiring extra work. The committee said the resulting change order totaled $20,812 to cover additional 4‑inch concrete and about 60 feet of additional curbing.
Council members asked how additional quantities arise after bids are awarded. A committee member explained that engineers estimate quantities for bids but underground utilities and other conditions found during excavation can increase work scope; after project completion the engineer measures actual quantities and confirms payment to the contractor. One council member cautioned that change orders can occur when low bids are submitted and extra work added later.
Public works also presented a plan for a Martin Road crosswalk near Jefferson School: a concrete pad and curb work estimated at $13,475. Staff said flashing beacons are optional and would cost about $5,000; the committee will discuss whether the school will contribute to the flashing lights.
The committee reported a tentative agreement for a half‑hour loading zone in front of Pace's Pizza on Third Street to support deliveries, and said Foot Avenue paving is nearing completion pending permanent striping.
The council did not adopt new policy at the meeting beyond committee approvals; staff will provide cost and signage follow‑up for the crosswalk and loading zone.