Committee records substantial-completion findings and construction updates for multiple school projects
Summary
The committee reviewed and recommended substantial completions and project updates for several storm-recovery and renovation projects, including Evergreen Junior High Ida repairs, H.L. Bushwell gym renovation, Ellender Memorial demolition credit, and construction progress at South Terrebonne and other campuses.
Get email alerts on the Construction Updates Substantial Completion topic
No spam. Unsubscribe anytime.
The Buildings, Food Service & Transportation Committee received multiple project updates and recommended substantial-completion determinations or progress reports for a series of school construction and renovation efforts.
For Evergreen Junior High (Hurricane Ida repair project Phase 2), the committee was presented a punch list and staff recommended a substantial-completion determination with a 45-day window for corrective items. For H.L. Bushwell High School competition gym renovations, staff showed before-and-after photos and said some finishes (banners, paint) and door painting remain; the contractor will finish remaining items prior to opening. For Ellender Memorial High School demolition related to Ida recovery, staff reported an anticipated $62,000 credit for unused costs and noted final grading of the elevated fill pad as a remaining punch-list item; new design submissions have been made to FEMA and staff will proceed after agency comments.
Staff also delivered a detailed construction update for South Terrebonne High School, reporting substantial progress on exterior canopies, windows (98% complete in pictured areas), auditorium sound panels (about 85% installed), corridor flooring on the second floor (about 35% complete), science labs nearing finish, and kitchen and cafeteria work progressing with inspections by the state fire marshal. The presenter said Thompson Construction is pushing to complete the site so that occupants can return by December if schedules hold; staff noted some remaining work on old gym spaces and terrazzo repairs.
The committee heard a program-level construction update that included South Terrebonne Middle School pile driving and foundation work, with about a month of schedule lag attributed to rain delays; the contractor reported work to achieve a concrete foundation by November if weather allows. Discussion touched on enrollment trends and local flood-insurance pressures affecting community decisions, and staff noted the availability of some private flood insurance options on the state insurance-commissioner website.
Several of these items were moved by committee motion and recommended to the full board for final acceptance or acknowledgement as appropriate; staff will continue to report progress and punch-list completion dates to the committee.