Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Frangio Road work continues; contractor cites rain delays and requests time extension

5786049 · September 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Kimley‑Horn and contractor Acosta reported Sept. 17 that work zones 1 and 2 are open, work continues in zones 3 and 4 and persistent rain has delayed completion; Acosta has requested three rain days be added to the contract and estimated phase‑3 finish in about one to one‑and‑a‑half months.

Kimley‑Horn consultant Stefano Viola and public‑information lead Janet Delgado updated the Town of Cutler Bay Council Sept. 17 on the Frangio Road improvement project, reporting progress across multiple work zones, ongoing drainage work and schedule impacts from heavy rain.

Viola said work Zones 1 and 2 are complete and open to the public, with a few tree relocations and sight‑line corrections remaining. He reported Acosta is performing concrete installation, earthwork grading and stabilization…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans