Committee recommends Site Works Solutions for Potter Lane park and detention pond; committee discusses pervious surfaces and budget gap
Summary
Streets and Sanitation recommended awarding the Potter Lane project to Site Works Solutions, discussed grant reimbursement (95% stated), options to value-engineer permeable pavers and parking surfaces, and noted a possible ~ $60,000 gap to finish the project.
Get email alerts on the Potter Lane Park topic
No spam. Unsubscribe anytime.
The McMinnville Streets and Sanitation Committee voted to recommend Site Works Solutions as the contractor for the Potter Lane project, a small park and detention-pond site, and discussed surface-material choices and budget implications.
Staff told the committee they received two bids; one was close to available grant funding and the other was significantly higher. The project is funded in large part by a grant: "95% of what we spend out of the 430,000 will come back," a staff member said. Staff said they expect to need roughly $60,000 in additional capital in the next budget to complete the work as currently bid.
The committee discussed design elements. Staff said the walking path was specified as a pervious surface and parking areas were listed as impervious in the plan, but that there was flexibility to use gravel or grass in places to reduce cost. The staff member confirmed the notice-to-proceed requires the contractor to "furnish or dispatch within 10 days after a written notice of award," and committee members asked staff to seek value-engineering options from the contractor to lower costs on path and parking surfaces.
Committee members raised landscaping and fencing details; staff said the plan calls for many new trees and that the perimeter will use a decorative farm-style fence rather than chain-link. The item will go to the full board for final approval; committee members voted to recommend the contract to the full board by voice vote.