Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Public Safety topic
No spam. Unsubscribe anytime.
County reviews design and $11M financing options for new public safety station; no action taken
Summary
Officials presented an 18,000-square-foot combined fire/EMS station concept and three financing options for approximately $11 million in total project costs. The board received the presentation and asked for further work sessions before any decision.
Get email alerts on the Public Safety topic
No spam. Unsubscribe anytime.
Amherst County officials presented a conceptual design and financing options for a new combined public safety station on Sept. 16 and the Board of Supervisors took no formal action, instead asking staff for follow-up work sessions on project timing and funding.
Fire Chief Beam introduced Jacob Caldwell of Dominion 7 (architect) and the county's design team. Caldwell presented an 18,000-square-foot single-story station with five apparatus bays, mixed career and volunteer bunk rooms (including separate female and volunteer spaces), a multipurpose training room that can serve as an emergency operations center, space for a sheriff’s office field desk and infrastructure such as a generator pad, diesel tanks and an on-site hydrant.
“...this is a station for today, tomorrow, and the next 40 years,” Chief Beam said, describing continuity-of-operations features that would allow temporary dispatch or emergency operations functions to operate from the station in a disaster.
Estimated costs and schedule
Architect and staff estimates put the building-and-site construction cost at roughly $9.3 million on the current schematic, with allowances and contingencies bringing a subtotal (construction plus allowances) to just over $10.3 million and a total project cost — including AE fees, third-party inspections, furniture and other allowances — to about $11.03 million. The presentation includes a 10% owner’s contingency, a $50,000 furniture allowance and allowances for security, cabling and special inspections. Staff said the estimated A&E appropriation for FY 2026 would be about $607,000, with construction planned for FY 2027 if the board moves forward.
Jacob Caldwell said the project’s site is Lot 5 in the Amelon Commerce Center and noted the facility’s rear-facing apparatus bays would allow two-sided exits for faster response.
Timeline: Chief Beam and staff estimated design and procurement plus construction would take a minimum of about 18 months if work began promptly; chief and architects noted design-build procurement approaches could shorten schedules but require separate board discussion.
Financing options discussed
The county’s financial adviser, Roland Keusch of Davenport, reviewed three financing pathways and their budget impacts:
- Direct bank loan (conduit via EDA): 20-year amortization assumed, planning rate ~5%. Lower overall interest cost but higher annual payments (estimated near $915,000 at peak principal-and-interest) and more near-term budgetary stress; total principal-and-interest roughly $18 million over life of loan.
- Virginia Resources Authority (VRA) pooled financing: 30-year fully amortizing example at about 4.5% yields lower annual payments (~$710,000) and more flexibility to structure repayments; second VRA example used a 30-year structure with a multi-year interest-only period to reduce near-term payments while increasing long-term interest costs slightly.
- USDA Community Facilities (direct USDA loan): taxable/subsidized options discussed; because current taxable rates were relatively high, the USDA option added program costs (including build-America/buy-America and Davis-Bacon wage requirements that can increase construction cost by 3–5%) and required a debt-service reserve fund, making near-term cash flow advantages limited in current markets. The USDA 40-year example raised total lifecycle P&I to roughly $28 million in the presentation.
Keusch emphasized the county faces a debt-service peak tied to recent landfill and other financings during 2027–2031 and that the county will need short-term bridging funds or additional recurring revenue to avoid budget pressure during that period. Keusch showed that once the county passes the 2032 debt-service drop, the public safety project could be absorbed into budgeted debt capacity; the challenge is bridging the near-term peak.
Board reaction and next steps
Supervisors asked for more work sessions to reconcile timing, the county’s capital plan and tax/revenue projections, and to consider trade-offs (e.g., higher near-term payments with lower total interest versus lower payments with higher long-term interest). Board members also raised operational questions about existing rescue-station arrangements and how current facilities would be used after a new station is built.
Chief Beam and the design team said they will provide the presentation files to staff and are available for follow-up. Roland Keusch recommended VRA as offering the most structural flexibility to mitigate near-term cash-flow pressure, while noting a direct bank loan reduces total interest expense if the county can meet larger near-term payments. No approvals or funding decisions were made; the presentation was informational and staff recommended additional work sessions.

