Board approves BG-1 to begin roof and building renovations at Baker and RDC; seeks construction manager

6439086 · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Clark County Board of Education approved BG-1 forms to begin design and bidding steps for roof replacements and renovations at Baker Intermediate and Robert B. Campbell (RDC) and authorized advertising for a construction manager; architects reported saturated roof cores and areas needing full deck replacement.

The Clark County Board of Education voted 5-0 to approve BG-1 forms to begin planning and design work for roof replacements and building renovations at Baker Intermediate School and Robert B. Campbell Junior High School and separately authorized advertising for a construction manager to coordinate the projects.

District facilities staff and architect Brian (We're All Star Architects) told the board the work will include a full roof replacement on Baker, targeted full-deck replacement at RDC where roof cores showed water saturation, HVAC unit replacements, window upgrades and building fire-alarm work. Brian said a combination of overlay and selective tear-off strategies is being priced to meet current energy code and wind-uplift requirements.

The board’s action allows staff to prepare BG-2/BG-3 documents and bring refined scopes and costs back to the board for later approval. The motion to approve the BG-1 was made by Board Member Kaiser and seconded by Board Member Dorsey; the motion to advertise for construction management services was moved by Board Member Dorsey and seconded by Board Member Hall. Both motions carried 5-0.

Why it matters: District staff said the projects are priority 1 in the district facility plan. The BG-1 is the administrative step that allows the district to produce construction documents and formally solicit contractor pricing; no construction contracts were awarded at the meeting and the board was not committing to final costs.

Details from the presentation and board discussion

- Architect findings: Drone and infrared scans at RDC showed areas of moisture infiltration; one core sample was saturated through the roof deck. Brian said the red-marked areas on the scan will require full replacement down to deck; other areas may be overlaid or scarified and re-coated. He described three roof system types at Baker (standing seam metal, spray foam and PVC) and proposed a metal overlay in some areas to avoid adding inches of insulation required by current energy codes if a full tear-off were performed.

- Warranty and maintenance: Brian said the proposed spray-foam recoat option would carry a 20-year warranty; the standing-seam overlay is also a long-life option. He recommended pricing the work for whole-building mobilization so warranties align and maintenance is simplified, while noting the board can reduce scope later to control cost.

- Schedule and next steps: Staff said architects will prepare more formal plans and cost estimates and return in the coming months with BG-2/BG-3 documents. Brian estimated further refinement would occur over the next 4–5 months.

Board action and votes

- Approve BG-1 for renovation projects at Baker Intermediate School and Robert B. Campbell Junior High School — Motion by Board Member Kaiser; second by Board Member Dorsey; outcome: approved 5-0.

- Approve advertising for construction management services related to upcoming renovation projects at Baker and RDC — Motion by Board Member Dorsey; second by Board Member Hall; outcome: approved 5-0.

What the board did not decide

The board did not award any construction contracts or commit to final scopes or budgets at this meeting; staff and the architect said the BG-1 is the initial step to develop detailed construction documents and obtain contractor pricing.

Ending: Architects and staff will return with refined plans and cost estimates; the board retained discretion to scale scope in subsequent BG-2/BG-3 phases.