City staff told the council the wastewater treatment plant electrical upgrade design is 90% complete and a staff workshop is planned Oct. 8, but state EFC grants appear unlikely and the city must decide whether to bond or seek EFC financing before bidding.

City staff told the Glens Falls Common Council on Sept. 23 that the electrical upgrade at the wastewater treatment plant is roughly 90% designed and that a workshop is scheduled for Oct. 8 to review plans and prepare bid documents.

A staff presenter said the city has pursued funding through the state Environmental Facilities Corporation (EFC) but was told the project “doesn't score well enough to receive funding” as a grant; staff said the city can obtain…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans