Ministry Village reports cleared site, new contractor and pending architect drawings
Summary
Ministry Village told the board it has cleared and surveyed its land, completed topo and geotechnical work, changed general contractors and is waiting for architectural drawings and a development order before construction proceeds.
Get email alerts on the Construction And Development topic
No spam. Unsubscribe anytime.
A Ministry Village representative updated the board on the nonprofit's planned recovery housing site.
The representative said the property has been cleared and surveyed; topographic and geotechnical studies are complete. Ministry Village reported it recently changed general contractors and expects construction to proceed faster as a result. The organization said it is awaiting two items before work can begin in earnest: finalized architectural drawings from its architect and a development order from the county.
The speaker asked county staff for assistance expediting the development order. The representative also said more than 300 women have applied to the program this year.
Ending
Ministry Village did not request formal board action at the meeting; the representative asked county staff to help move the development-order process along.