Riviera Beach USD approves $2.42 million change order, receives updates on water‑plant work
Summary
The Riviera Beach Utility Special District on Sept. 10 authorized a $2,422,818.02 change order to Haskell CDM Smith JV for an added Floridan‑aquifer well, pilot testing and related design work, and heard progress reports from contractors on well rehabilitation, pretreatment piloting and membrane selection for the new treatment plant.
The City of Riviera Beach Utility Special District on Sept. 10 approved a change order not to exceed $2,422,818.02 to the Haskell CDM Smith joint venture to design and construct one additional Floridan aquifer well, perform additional pilot testing, make roadway and drainage improvements on Avenue L, and modify pretreatment systems for the new water treatment plant.
The measure, listed as Resolution 24‑25UD, passed unanimously during the special utility district meeting. The board heard a series of contractor updates beforehand from the city's owner's representative and vendors working on the existing and new plants.
Nigel Grace, the city’s owner's representative with Brown & Caldwell, told the board the change order stems from two developments during design: the plant’s design capacity increased from 12 million gallons per day (MGD) to 14 MGD, creating a need for additional raw‑water supply, and pretreatment sampling and piloting showed more extensive pretreatment will be required than originally planned. Grace said additional piloting and engineering work — including a roughly $700,000 pilot investigation described during the meeting — are included in the requested change order. "That also necessitated the design of a much more elaborate pretreatment system that was not originally envisioned," Grace said.
Co…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat