Board hears updates on poles, new substations, easements and generator operations
Summary
Staff updated the board on pole setting and line work at 1100 East, three drilled foundations completed, an outstanding easement needed from the Richardson property, progress on Transformer 2 and the Sky Mountain substation bid packages, and the status of city generators and seasonal running.
Get email alerts on the Infrastructure Operations topic
No spam. Unsubscribe anytime.
Staff reported progress on several capital and operating items: pole setting on a line described as "1100" (most poles set, with a few yet to be installed), three drilled foundations poured during recent drilling work, and a remaining easement needed where the distribution line will overhang the Richardson property. Staff said they were working with property owners to secure the easement and cannot string the line until the easement is obtained and concrete cures.
On substation work, staff said Transformer 2 is near completion and expected to be placed into service soon. At Sky Mountain substation, the control building and perimeter wall are being bid as the next construction phase; staff described the control building as a smaller version of a recent substation building and explained the contractor bidding strategy (general contractor for building and wall, then separate bids for electrical/site work).
Generation updates: staff said the city's standby generators are "in pretty good shape" and that seasonal running would wind down as temperatures cool, though higher market prices prompted scheduling of additional generation the day after the meeting. Crystal (referenced in the meeting) is monitoring weather and dispatch decisions.
Operations and maintenance anecdotes included work at Interstate Rock where staff repair and bill time-and-materials for infrastructure on private property that supports the crusher; one recent outage involved an arm that split and a conductor that contacted a grounded arm and blew a fuse, which staff repaired.
Staff also described ongoing trimming, termination work on cable ends, and preparations for Peach Days (temporary power at event venues and banners).
Direct excerpt from the meeting audio: "We've got, I think, all but, let's see, 4, 5 all but 5 poles set," and staff noted "We need an additional easement where the line's gonna overhang onto the Richardson's property right there." The board received the updates and did not take formal action on these operational items.