Jefferson City Schools get construction update: early childhood center nearly complete; middle school additions on accelerated schedule
Summary
Contractor SM Wilson told the Jefferson City School Board the early childhood center is about 97% complete, several middle-school renovation phases are ahead of schedule and the Jeff City Academic Center demolition is under way, with completion dates ranging from Thanksgiving to next August.
Patrick Aylsworth of SM Wilson updated the Jefferson City Board of Education on bond-funded construction projects, saying the district's early childhood center is approximately 97% built and that multiple middle-school renovations are moving faster than originally planned.
The presentation covered three active sites: the early childhood center, Lewis and Clark and Thomas Jefferson Middle School renovations, and the Jeff City Academic Center. Aylsworth and the project's senior manager, Emily, described work completed this summer, ongoing interior finishes and the phasing plan that the contractor and district developed to shorten the schedule.
Aylsworth said the early childhood center project — which the team began in February 2024 — wrapped construction work in August and is now at about 97% completion as subs…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat