Board hears construction progress at high school and updates on bus barn and middle‑school land purchase
Summary
District operations staff updated trustees on high school punch‑list items, bus‑barn progress, Frontier bus drop use, Legacy Gym AC delivery, and a pending minor plat and title work for planned middle‑school property acquisition.
Get email alerts on the Facilities And Operations topic
No spam. Unsubscribe anytime.
Operations staff reported progress and remaining work on multiple district construction and grounds projects.
At the new high school, staff said most systems are operational: parking‑lot lighting is installed, the elevator is working, donor plaques and legacy walls are in place, carpet and flooring are complete, and band/vocal sound issues have been corrected. Staff said remaining punch‑list items include installation of the back stage curtain, completion of an archway trophy case, permanent mechanical‑room lighting, and HVAC control programming; the engineering firm IMAG was scheduled to return to commission the building and turn controls over to district staff. Staff said they hope to substantially complete outstanding items by the end of the month.
The operations report said the bus barn (operations shop) has doors and windows installed and mechanical rough‑ins completed; electricians and plumbers will finish final work after interior finishes and the concrete valley gutter are completed. Staff projected the bus barn could be substantially complete by early October.
A new bus drop‑off area at Frontier was used for the first time on the first day of school; landscaping and lighting work remain. Legacy Gym’s replacement AC unit arrived the day of the meeting and installation work was starting.
On the planned middle‑school site purchase, staff said they are awaiting city approval of a minor plat and completing a title search. Soil borings and a survey are scheduled once harvest (soybean) operations in the field are finished. Staff said roughly 10% of the parcel includes a low/wet area and that detention/runoff needs can likely be incorporated into the site plan.
Board members asked when punch‑list and closeout activities would be finished; operations staff projected completion timelines by the end of the month for the high‑school items and by early October for the bus‑barn work. Staff also noted continuing coordination with architects and engineers for training and system commissioning.