Baldwin Park updates San Gabriel River Greenway construction; stairs poured, October completion targeted
Summary
City public works director reported construction progress on the San Gabriel River Greenway, including poured stairs, irrigation work, and a target completion date of Oct. 31, with contract change orders and permitting delays noted.
Daniel Padilla, Baldwin Park director of public works, told the City Council on Sept. 17 that construction of the San Gabriel River Greenway is advancing and that "the stairs were poured yesterday." The project is installing stairs, irrigation, lighting, security cameras, a drinking fountain, a bike path connection and decorative fencing and gates.
The presentation said the original contract amount was about $1,900,000 and that the council approved a $130,000 change order for escalation. Padilla said the contract also included a…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat