Victorville adds 5% contingency to Greentree library project, authorizes $1.293 million in change orders
Summary
The council approved increasing contingency for the Greentree library renovation and expansion (JM 24-051) from 10% to 15%, adding $431,050 and authorizing cumulative change orders not to exceed $1,293,150; the project is largely funded by a $9 million California State Library grant.
The Victorville City Council on Sept. 16, 2025 voted unanimously to increase the contingency for the Greentree library renovation and expansion project (Project JM 24-051) from 10% to 15%, representing an additional $431,050. The council also authorized the city manager or designee to execute change orders up to a cumulative total of $1,293,150 reflecting the 15% contingency.
Staff said the city was awarded a $9,000,000 grant…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat