The board granted a six‑month extension to March 21, 2026, for an amended approval involving migrant farmworker housing at 11 Gerda Lane and authorized counsel to draft a revision to condition 5(b) to allow chair signoff after agreed assurances.
Get email alerts on the Housing Farmworker topic
No spam. Unsubscribe anytime.
The Town of Goshen Planning Board on Sept. 3 granted a six‑month extension to March 21, 2026, for an amended conditional approval affecting migrant farmworker housing at 11 Gerda Lane and authorized the town attorney to prepare an amendment to condition 5(b) of that approval.
John Furst submitted a written request on behalf of the applicant seeking another extension and a slight modification of condition 5(b). The letter said the Orange County Department of Health (DOH) had approved the water system but would not issue the operations permit for migrant farmworker housing until the water system was installed; the applicant cannot install the water system until it owns the property, and closing is contingent on the chair signing the final plans. The letter described a Catch‑22 and requested the board allow the DOH operations‑permit requirement to be met prior to issuance of a certificate of occupancy rather than before the chair signs the final plans. The applicant offered to post a performance guarantee if needed.
At the meeting, counsel reiterated that DOH had inspected the housing and was ready to issue the operations permit once the water system was installed, and the parties discussed tying any waiver or condition to a recorded assurance or letter from staff rather than requiring physical installation before plan signing. The board voted to grant the six‑month extension to March 21, 2026. Later in the meeting the board voted to authorize counsel to prepare an amendment to condition 5(b) to address the DOH/plan‑signing issue and related assurances.
Why it matters: the extension and the authorized condition amendment aim to resolve a timing impasse that prevented the applicant from closing on the property and completing required DOH and planning board steps. The board recorded its direction to have counsel prepare the revised language for the board’s next meeting.
No final modification to condition 5(b) was adopted at this meeting; authorization was limited to drafting proposed language for future board action.