Developer seeks annexation and phased buildout for Hideout Mountain Village; council continues review
Summary
Developers updated the council on the Hideout Mountain Village annexation plan, which proposes stacked flats, townhomes, single-family lots, trails and a town-dedicated pickleball facility; the council continued review to Oct. 9 for additional engineering review and a site visit.
Get email alerts on the Land Use And Annexation topic
No spam. Unsubscribe anytime.
Hideout — Developer representatives presented an updated concept and development agreement for the Hideout Mountain Village project at the Sept. 11 council meeting and the council voted to continue the matter to Oct. 9 to allow staff and the applicant to resolve technical questions.
Nate Brock, representing the applicant, walked through a detailed concept plan for multiple residential product types, onsite trails and recreational amenities, and a commercial pad the developer described as a possible small retail/food site. Brock said the developer’s intent is to provide a mix of housing types and community amenities, including an indoor pickleball facility the developer proposed to dedicate to the town if built.
Council and staff discussion focused on technical design issues raised by the town’s engineering review: the location of the public-utility easement (PUE) relative to the curb and sidewalk, retaining-wall heights and soils/rock conditions for detention basins, the steepness of several trail segments and proposed stair alignments, and where storm and sewer flows connect to existing town or district systems. Town staff also asked the applicant to clarify which amenities are required by code and which are offered as extra community benefits.
The applicant acknowledged several changes made since the earlier submittal. Brock said the PUE placement affects front-yard building envelopes; the developer said it could accept the town engineer’s preferred alignment if the council directs that change, though that would reduce a small amount of open-space acreage in the plan. Brock also said the team will provide an updated set of design drawings and confirm where wetlands or constrained areas affect lot layout.
Council members asked for a site visit with staff, the applicant’s engineers and the planning commission before the next hearing. Several council members emphasized that retaining-wall heights, cut-and-fill quantities on steep slopes and safe road grades need engineering confirmation before the council takes land-use action. The council voted to continue the annexation and development agreement to the Oct. 9 meeting.
Why it matters: The annexation and development would add several dozen residential units and new public amenities; it raises typical planning issues for mountain land—slope, drainage, and long-term maintenance of trails and private drives—that will affect both town infrastructure and residents’ safety.
What’s next: Staff and the applicant will resolve engineering clarifications, return revised drawings, and schedule a joint site visit with the planning commission and council to review retaining-wall alignments, PUE placement and other technical matters ahead of the Oct. 9 continuation vote.