Secondary roads update: bridge work, Hancock paving adjustments and motor grader operator vacancy posted

5779419 · September 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County engineering gave updates on bridge pours and guardrail schedules, changed the Hancock Avenue paving approach to add a strengthening course, and the board approved posting for a motor grader operator at Eagle Grove with tiered step pay.

Wright County’s secondary roads office updated the Board of Supervisors Sept. 15 on bridge and paving projects and received approval to post a motor grader operator vacancy.

Engineering staff reported the guardrail contractor will pour bridge approaches on Thursday and Friday of the following week, delaying guardrail installation by one week; that change shifts the anticipated opening of the Vospori bridge to around Sept. 30, subject to weather and completion of backfill and guardrail installation.

On paving, crews applied an intermediate lift on Hancock Avenue from Highway 3 south and decided to add a strength-and-leveling course (about 1/2 to 3/4 inch) on remaining sections to address low spots and reduce overrun on the intermediate lift. The contractor had completed about a mile of the leveling lift and work would continue with intermediate and surface lifts; railroad approach sections will be completed under standard railroad approach plans.

The board approved posting a vacancy for a full-time motor grader operator based at the Eagle Grove maintenance facility. The posting sets starting pay at $28.30 per hour for six months (50 cents below base), then $28.55 for the next six months after a positive review, and $28.80 at one year. The position will be posted for a minimum of 10 days, with a current close date set to Oct. 9 at 3:30 p.m.

Staff also reported progress on guardrail backfill, sign replacement and ongoing gravel hauling and blading operations in secondary roads.