Budget committee approves $76 million increase to SFO project management contract for Terminal 3 modernization
Summary
The Budget and Finance Committee voted 3-0 to forward a resolution approving Modification No. 15 to WCME JV’s project-management-support contract, increasing the not-to-exceed value to $126 million and extending the contract through Dec. 12, 2030.
Get email alerts on the Airport Projects topic
No spam. Unsubscribe anytime.
The Budget and Finance Committee on Sept. 17 voted to forward to the full Board of Supervisors a resolution approving modification number 15 to the San Francisco International Airport’s project-management-support contract with WCME JV for the Terminal 3 West modernization project.
The amendment increases the contract by $76 million, bringing the not-to-exceed total to $126 million, and extends the contract term through Dec. 12, 2030. The committee recommended approval by a 3-0 vote.
Scope and funding: SFO officials said WCME JV provides project-management oversight, including project controls, cost and schedule management, budget analysis and cost estimating, and monthly reporting. The Terminal 3 West modernization project covers seismic retrofit, replacement of end-of-life building systems, additional swing gates, a new TSA checked-baggage-inspection system, expanded concessions and a larger security checkpoint, replacement of façade elements and the construction of a Courtyard 4 connector building to accommodate airline lounge and office space. The project budget has grown substantially since 2017; presenters documented an increase from roughly $627 million in 2017 to about $2.8 billion currently.
Airport funding and minority/local participation: The contract is funded by airport revenue bonds under SFO’s capital-improvement plan, and the Airport said there is no impact on operating costs. The prime joint venture exceeds the airport’s local business enterprise subconsulting participation requirement: WCME JV reported 30.7% subconsultant participation against a 20% requirement.
Budget office findings: The Budget and Legislative Analyst recommended approval and noted that while the contract increase is substantial in absolute terms, it remains proportional to the enlarged project budget (about 4–4.5% of total project cost as presented).
Vote and next steps: The resolution was forwarded to the full board with a positive recommendation. Committee members asked whether the overall scope had increased since the contract was originally approved; SFO staff described added elements including the Courtyard 4 connector building, an east addition nearer the E gates, full replacement of the landside façade, and an overhaul of the pre-security lobby and baggage systems. The committee recorded a 3-0 roll call in favor.
Ending: The contract modification will proceed to the Board of Supervisors for final approval; SFO officials and the BLA will continue to update the committee and the board as the modernization work progresses and additional funding or scope changes arise.