Madison County approves consultant work to update construction standards and advance Bridal 45 design
Summary
The Madison County Commissioners approved a county construction‑standards review and a local public agency (LPA) consulting contract for Bridal 45 (County Road 300 West over Lehi Creek), and accepted a task order to update county construction standards.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
Madison County commissioners approved a consultant task order and two contracts during a county meeting, approving a county construction‑standards review and a local public agency consulting contract for the Bridal 45 bridge project.
County Engineer Jessica said the first item is a task order to update the county's construction standards, and that the work is estimated at $11,000 and will be funded from an existing on‑call contract and appropriated budget. "It's quite possibly one of the more boring things that I work on," Jessica said, "but very important." The commissioners voted to approve the county standard review with Aegis.
Jessica also presented a local public agency (LPA) consultant contract for Bridal 45, County Road 300 West over Lehi Creek, saying the contract has been negotiated and reviewed by INDOT. The contract sets a maximum payable amount of $412,400; Jessica said the project will span two to three years depending on INDOT approvals. She also said the county has been awarded construction funding described in the record as "the $80.20," but did not clarify the full figure or units in the record. Jessica said the county is seeking INDOT preliminary engineering and right‑of‑way funds that could reduce the county's share of design costs.
Commissioners voted to approve the LPA consulting contract. The record shows the board's motions and seconds carried and the votes were recorded as "Aye. Motion carries." The meeting record does not include individual roll‑call votes.
The approvals follow the county's effort to modernize technical and appearance standards and to advance federally funded rural aid projects. County staff said the standard updates aim to remove contradictory language in older documents and align county standards with current industry practice.
The commissioners also approved related procedural steps: staff reported the task order is within budget and the LPA contract is a standard INDOT form.
Looking ahead, county staff said INDOT must approve any design funding awards and that the Bridal 45 project schedule depends on INDOT's allocation of preliminary engineering funds.