City manager reports progress, delays on Lakeway transportation bond projects; Wild Cherry/Flint Rock signal expected in early 2026
Summary
City Manager Joseph updated council on a $17.5 million transportation bond program that has funded culverts, resurfacing and traffic signals; some projects are complete, several are delayed pending developer work or complex site conditions and a new $3 million CAMPO grant application could add major trail improvements.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
Lakeway’s City Manager Joseph gave a status report Sept. 15 on projects funded by the $17.5 million transportation bond the city approved in 2022, highlighting culvert upgrades, road resurfacing and several signal/traffic projects while noting timing uncertainties on Main Street and Burrell Street work.
Key accomplishments and current status
- Culverts and drainage: The city completed culvert upgrades at Lakeway Drive and Top of the Lake; both performed well during July flooding, Joseph said.
- Resurfacing: Mill-and-overlay resurfacing finished on Lakeway Drive, Lakeway Boulevard and Lomond’s Crossing.
- Traffic signals: A signal at 620 and the Bella Montagna access (Flamingo/Palazzo Alto) is operational in a temporary configuration pending the future 620 widening. The Wild Cherry and Flint Rock Road signal is under construction; staff expects work to begin in October with completion targeted for January 2026.
- Burrell Street and Main Street: The city has completed a feasibility study that recommends a re-aligned Burrell Street to reduce bridge span and avoid floodplain; geotechnical work is under way and staff is negotiating right-of-way acquisition with a cooperative property owner.
Grant opportunity and next steps
- Joseph said staff has advanced a Capital Area Metropolitan Planning Organization (CAMPO) grant application that, if awarded, would fund about $3 million in multimodal improvements along Lakeway Boulevard; Lakeway’s match would be approximately $800,000 if the city chooses to accept the award.
- Staff reported the bond program remains generally in good standing — several projects came in under budget, freeing funds for additional work — but cautioned that upcoming bridge and intersection projects will consume reserves.
Quotes and concerns
- About Flint Rock Road, which traverses multiple jurisdictions, Joseph told council: “It’s a very challenging road due to its topography,” and described improvements that are in progress including signage, grooving on curves and a potential radar speed sign at the Serene Hills approach.
- Council members pressed for clearer timelines on Highlands Boulevard pedestrian improvements and the HAWK signal at Highlands and Tavish Trail; Joseph said the consulting engineer expects design work in the weeks ahead and that construction phasing and power issues are being resolved.
Ending
Council took no action; the report will return to a future meeting as projects advance and staff refines costs and schedules.