At a Property Management Committee meeting, the mayor outlined a quarterly capital projects list that includes buying the Bank of America building, an expanded first‑responder admin site, convenience‑center needs in La Verne, juvenile‑court expansion and an accelerated adult detention study.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The mayor of Rutherford County told the Property Management Committee on Tuesday evening that the mayor's office will deliver quarterly capital‑projects updates and asked the committee to help set priorities for a list that includes purchase of the Bank of America building, a first‑responder administration site at 814 South Church, convenience‑center replacements, juvenile court expansion and an accelerated study for a new adult detention center.
The mayor said the Bank of America building on East Main is under contract for $9.2 million and that county staff are conducting standard due diligence, including a 120‑day inspection window. "It is my hope … that by end of this year, we can begin the process we can close on that piece of property," the mayor said. He asked the committee to weigh in on departmental programming so that offices displaced by needed repairs to the Goldstein building can be moved into the new space if appropriate.
Committee members were shown a prioritized 12‑month list and told the mayor's office will bring the committee back every three months and give monthly updates on active construction sites. The mayor described this presentation as a vision, not a funding request: "I'm not coming to you and asking you to fund these. That's not what this is about tonight. This is about … here are the projects. I'm asking you to consider these projects."
Key projects on the mayor's list
- Bank of America building (East Main): Under contract for $9.2 million; due diligence in progress and a 120‑day review window for inspections. The mayor said staff hope to close and begin renovation work before year end.
- First Responders Administration Building, 814 South Church: A two‑story, roughly 10,000‑square‑foot building the county received from the school system. The mayor said the site was purchased for about $1 million and is subject to a conservation/flood‑easement constraint that limits some uses; he proposed using the building for county fire department administration and EMA functions and noted Chris Clark with Emergency Management has expressed interest in training space there.
- Convenience centers and transfer station planning: The mayor said the county must find a roughly 5‑acre site to replace a convenience center in La Verne after its current operator announced a closure. He described the cost to build a new transfer station as in the $1.5 million–$2 million range and asked the committee, and specifically Commissioner Davidson, for help locating suitable sites.
- Juvenile court expansion: Judge Lampley has advocated for more courtroom space. The mayor estimated the cost as roughly $1.5–$2.5 million and said the mayor's office may bring an architectural scope to the committee in the next two to three months.
- Adult detention center: The mayor said population pressures have escalated planning timelines for a new adult detention center, and he recommended increasing the project’s priority (see separate article).
Other items and next steps
The mayor reported that certain projects — including the Plainview Public Health and Safety building and the transfer station — are at different stages of completion and that detailed cost estimates are not yet available for larger projects. He asked commissioners to provide feedback on priorities so the mayor's office and the commission can jointly refine the list and later identify funding needs during the budget and appropriation process.
"This is a collaborative effort," the mayor said, asking commissioners to participate in programming needs for departments to be relocated from the Goldstein building and to help set priorities before the mayor presents specific appropriation requests to budget committees.
Ending
The mayor said the office will return with updates every three months on the capital list and with monthly progress reports for active construction projects such as the Bank of America property and the forensic center. No funding approvals were requested during the meeting.