Salinas council orders rebid of Sherwood Recreation Center contract after labor-compliance concerns; redirects CDBG funds to cover cost gap
Summary
The Salinas City Council voted Sept. 9 to reject awarding the construction contract for the Sherwood Recreation Center building improvements and directed staff to rebid the project after concerns surfaced about prior labor violations by a listed subcontractor.
Get email alerts on the Public Works Construction topic
No spam. Unsubscribe anytime.
The Salinas City Council voted Sept. 9 to reject awarding the construction contract for the Sherwood Recreation Center building improvements and directed staff to put the project back out to bid after labor-compliance concerns were raised about a subcontractor associated with the apparent low bidder.
The rebid direction followed a staff recommendation to award the contract to Auto Construction, the apparent lowest responsive bidder, for an amount not to exceed $2,686,900. Public-works staff told the council Auto Construction’s bid was about $88,000 below the engineer’s estimate and roughly $180,000 below the second-place bidder, and that the company had satisfied license and registration checks required under the city’s municipal code and the California Public Contract Code.
Council members and members of the public pressed staff and the city attorney for additional detail after labor advocates and several construction workers testified that a subcontractor, identified in public comment as B & M, had prior wage-and-hour violations and had not fully resolved related complaints in other jurisdictions. Council members asked whether those past problems should disqualify Auto Construction as a “responsible” bidder. The city attorney pointed to the responsibility criteria in the city’s municipal code (section 12‑23) and said staff had checked contractor license board and Department of Industrial Relations listings and found no active debarments or suspensions for Auto Construction.
Staff also described the city’s existing labor‑compliance tools: a city labor‑compliance officer, monthly certified‑payroll review tied to contractor payment, and the ability to withhold payment when certified payrolls are missing or show violations. City staff told the council the Auto Construction prime had provided a written commitment to oversee its subcontractors and to enforce labor compliance on the project.
Despite those assurances, several council members said they remained concerned about enforcement in the field. Labor representatives and a number of speakers at the council meeting said promises on paper had not prevented wage theft in other public projects and that workers were often afraid to complain. Contractors and some property managers pushed back in public comment, warning a rebid could cost the city more money and delay a project they described as long‑overdue.
After debate, Council Member Gloria De La Rosa moved to reject all bids and direct staff to rebid the Sherwood Recreation Center building improvements project; the motion passed on the council floor. Council discussion also noted that the project has been active for several years—city staff said work on the facility dates back to 2015 and that the city has spent roughly $8 million–$10 million to date on prior phases. Staff said the current contract would complete ADA and roof/window work identified after earlier phases.
Funding and federal rules: staff advised the council the project is funded in part with federal Community Development Block Grant (CDBG) dollars, which limits the city’s ability to impose local hiring preferences. City staff said federal requirements preclude adding local‑hire mandates on projects that use CDBG funds, and the city would instead rely on contractors’ outreach and the usual certified‑payroll enforcement. Council members asked how the city could still promote local hiring; staff said the only practical options would be (a) to decline the federal funds and look for a different funding source or (b) structure future procurements differently.
CDBG amendment approved: separately but related to Sherwood funding needs, the council later approved a substantial amendment to the FY 2023–24 CDBG annual action plan to redirect $595,000 to the Sherwood Recreation Center project. Of that amount, $550,000 was reallocated from the Republic Café/Chinatown building project and $45,000 from unspent public‑service funds for tenant/landlord assistance in 2023–24. Staff told the council the Republic Café site is still in pre‑development and that moving money to a project ready for construction would help maintain the city’s overall CDBG timeliness ratio. The amendment passed on a recorded vote.
What the council did and what comes next: the council’s formal action rejected staff’s recommendation to award to Auto Construction and instructed staff to rebid the Sherwood project. Staff said rebidding will require re‑advertising the plans and specifications and that the city would continue its labor‑compliance oversight on any future contract. Because bids came in below some estimates, staff warned rebidding could result in higher prices; at least one council member explicitly noted that rebidding may risk increased costs and said that if council members were uncomfortable with the recommended award, the safer course was to rebid.
Why this matters: the Sherwood Recreation Center improvements have been a multi‑phase effort to repair an aging facility used by seniors, youth and families. The project has drawn scrutiny because (1) it is federally funded, which limits local preferences; (2) it touches on broader local debates about labor standards, wage theft and enforcement; and (3) the city has sought to complete years‑long upgrades without further delay.
Council and staff contacts: the staff presentation and the council’s public discussion cite the municipal code procurement rules and the California Public Contract Code as the governing procurement authority; the city attorney also referenced municipal code section 12‑23 in explaining responsibility determinations.
Pending and follow‑up items: staff will rebid the Sherwood Recreation Center project, continue labor‑compliance monitoring, and return to council with procurement results. The city’s CDBG office will also manage the reallocation approved Sept. 9 and continue tracking the city’s timeliness ratio for federal grant compliance.
Speakers and public records: staff’s memo, bid tabulations, contractor correspondence and the public meeting record— including letters from labor organizations and contractor responses—are part of the project file in the public works division.