New Hoke County school project 'on schedule,' contractor payments at 58%; contingencies reduced after changes
Summary
District staff reported substantial progress on the new school: contractors are roughly 58% paid, building is dried in, glazing installed and finishing work underway. Contingency reserves have been used for design and owner items; known change orders near $1 million are under review.
Hoke County Schools staff told the board on Sept. 9 that construction on the district’s new school is on schedule and moving into interior finishes, while budget contingencies have been drawn down as change orders are reviewed.
The construction presentation said the general contractor has received about 58% of contract payments and the site and building are entering the finishing phase: curtain glazing is being installed, ductwork insulation is underway, drywall is beginning to go up and the main entry and pick-up/drop-off loop are substantially formed. The common learning stair, trophy-case areas and an elevated…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat