The Norton Planning Commission approved final site plan SPR 13‑2025 for a proposed development that lists Inspire Brands as the tenant, commissioners said at a meeting.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Norton Planning Commission approved final site plan SPR 13‑2025 for a proposed development that lists Inspire Brands as the tenant, commissioners said at a meeting. The commission's reviewing engineer recommended approval after most technical comments on the traffic impact study (TIS) and the site plan were addressed, the commission heard.
The commission's zoning administrator summarized engineering comments and said the engineer, identified in the record as Binsley, “recommends approval.” Ken Knuckles, representative of Development Management Group of Nashville and the applicant's representative, told commissioners the applicant had addressed the outstanding TIS and site‑plan comments and could comply with the remaining items.
Why it matters: the project includes circulation changes, a new driveway on the applicant's frontage and a fuel offloading station for on‑site generators that some residents described as close to nearby homes. The commission approved the site plan so the applicant can proceed to required permits in Barberton, but commissioners and residents pressed for clearer technical details about the fuel system and utility connections before construction begins.
Commissioners and staff discussed a handful of remaining technical items. Knuckles said the applicant had removed a shared access and would construct its own driveway on the frontage, which the applicant and commission members agreed should improve truck circulation. The zoning administrator and the applicant said engineer Binsley had requested only minor adjustments — primarily to an inner driveway at the north end — and that those adjustments were being made.
Resident Glenn Yasco asked who owns the property at 3700 Limestone Drive; staff said they had not resolved ownership at the meeting and pointed to the auditor's office records cited by Yasco. The record shows the auditor indicated Dominion Field Service was listed as having paid the most recent taxes; staff also said FirstEnergy could be involved. The commission did not take formal action on property ownership.
Several speakers sought clarity about the project's proposed fuel handling and backup generation. Commissioners and residents expressed uncertainty in the record about whether the site would use utility natural gas or liquefied propane and whether fuel deliveries would come by truck or rail. A commission member summarized the concern: “Is it offloading liquid propane then? From a tanker car. Yeah. From a From a tanker train delivered?” That exchange in the record shows commissioners want the applicant to clarify the fuel type, offloading method and any safety measures before final construction approvals are completed through Barberton and other agencies.
Commission members asked the applicant to produce a frequently asked questions document and to provide more technical detail on utility, water and gas connections when the application is resubmitted. The zoning administrator told the commission that several items tied to the city of Barberton (shore/water approvals and construction plan items) remain part of the construction‑permit process and are separate from final site plan approval by the Norton Planning Commission. Commissioners noted the TIS adjustments so far appeared minor; one participant described a possible change from “175 to 177 cars” as illustrative of the small numerical tweaks still under review.
The motion to approve PC application SPR 13‑2025 passed on a roll call that recorded “Yes” votes from Commissioners Peterson, Witzberger, Leyda and Dowling. The commission noted that final construction permitting and any outstanding Barberton utility approvals are the applicant's next steps.
The commission also approved its minutes from the Aug. 12 meeting during the same session. Staff updates at the end of the meeting noted personnel changes: Miss Snyder will move to the service department and Sam Owen will replace her in the staff position referenced in the record.
The commission's discussion and the record make clear that, while final site‑plan approval was granted, technical clarifications about fuel type, offloading method, and several construction‑plan items remain to be resolved with the applicant and the city of Barberton before construction begins.